BERNARDS TWP – A fight against plans for a new Millington
Baptist Church on Mine Brook Road continued before the Planning
Board on Tuesday, May 17, as objectors presented legal arguments
that would send the seven-year-old proposal back to square
one.
Karen T. Del Vento of 397 Mine Brook Road, who is an attorney,
maintained that the board could not grant final site plan
approval for the project because the application was received
after the preliminary site plan approval expired.
Under that scenario, Millington Baptist might need to apply
for a new preliminary site plan.
Although Millington Baptist’s attorney, David Ramsey,
challenged the argument, Board Attorney Stuart R. Koenig
said there were unanswered questions. He asked Del Vento
and Ramsey to submit briefs for his review.
“I do think it’s an issue that should be reviewed
by the board,” Koenig said. “I do think it needs
some analysis.”
The hearing, which drew about 105 people both for and against
the proposal, lasted more than three hours before it was
carried to 7:30 p.m. Tuesday, July 19.
If that hearing proceeds, the objectors plan to present
testimony from two expert witnesses – an engineer and
an environmentalist.
Millington Baptist, now located at the corner of Valley
and King George roads, is seeking to build a 67,390-square-foot
complex with up to 1,200 seats, 21 classrooms for Sunday
school and 403 paved parking stalls on 88.9 acres in a three-acre
residential zone.
The project received preliminary approval in a 5-4 vote
in August 1999, following seven stormy hearings in which
large crowds attacked its size and scope. The objectors later
tried and failed to overturn the approval in court.
Because the project was outside the municipal sewer district,
it also needed state Department of Environmental Protection
(DEP) approval to allow a septic disposal field near the
Dead River. After a four-and-a-half year review, the DEP
granted a final permit in April 2004.
A request for final site plan approval is usually little
more than a formality. But the objectors have said it should
denied due to changes made since the preliminary approval.
Church officials maintain that the changes were largely unregulated
aesthetic improvements.
Last Tuesday’s hearing, the fourth on the final plan
site request since Dec. 7, was to begin with the objectors’ case,
since Millington Baptist had completed its presentation.
Ramsey, however, said he wanted to recall the project architect
to address interior lighting on a bell tower.
Disclosure Issue
But before Ramsey could do that, Koenig noted that Stuart
J. Lieberman, a Princeton attorney representing two objectors,
had raised another legal issue.
That issue was whether Millington Baptist’s consultants
needed to disclose any political campaign contributions in
accordance with a township ordinance adopted last Oct. 26.
The ordinance required disclosures from developers needing
a variance for a preliminary site plan approval.
Lieberman, while conceding that the preliminary approval
preceded the ordinance, said the ordinance should apply to
the final plan because it was designed “to curb bad
past practices.”
Ramsey disagreed, saying if a variance was already granted,
it made no sense to apply the ordinance to a final site plan
requiring no relief from zoning standards.
Koenig agreed that the ordinance should not apply. The board
concurred in a 7-2 vote, with Richard Macksoud and Bert Fonde
dissenting.
Project architect Ben Lee then testified about the bell
tower lighting. The tower, which would have no bell, would
be 85 feet high, with an opening between a height of 52 and
57 feet, topped off by a spire.
Lee said that at a height of 22 feet, each side of the tower
would have a band of four light bulbs, of which two would
point down and two would point up. There would be a total
of 16 bulbs.
Lee posted two computer-generated pictures of how the tower
would look at night. But he said the picture showed the tower
being more illuminated than it would actually be.
Lieberman and 10 residents went on to question the lighting
level.
“What else isn’t on this incredibly large, invasive
structure?” asked Laura Neff of 430 Mine Brook Road
in Far Hills. “I don’t think you know.”
After Lee stepped down, Del Vento presented her legal arguments
against further hearings.
Del Vento said the preliminary approval, which the board
formally memorialized on Sept. 7, 1999, was good for three
years and received the maximum of two, one-year extensions,
leading to a final expiration on Sept. 7, 2004.
But Millington Baptist did not formally file for a final
site plan approval until Sept. 23, 2004, she said. She then
cited a state court ruling that allowed Point Pleasant to
reject a request for final site plan approval because the
preliminary plan had expired.
Ramsey disputed Millington Baptist’s preliminary expiration
date. He noted that the board, in response to a lawsuit from
the objectors, voted to amend the approval on Oct. 3, 2000.
Ramsey also saw differences with the Point Pleasant zoning
ordinance, saying Bernards appeared to allow more leeway.
He said if the board had not applied an expiration date
to other proposals, it could not do so for Millington Baptist.
Koenig said he needed to know more. “I don’t
recall the Planning Board having to face this issue.”
Copyright 2005 The Bernardsville News |